Reconstruction of runway Warsaw Airport
02/09/2010
Work on the runway intersection, scheduled for September 2010, does not mean the airport will be closed to all traffic. A shortened 1300-metre runway will remain open for smaller passenger aircraft with a capacity of about 50 seats.
The work is scheduled to take 4 days to complete and will be carried out during the first three weekends in September:
- 3 Sept 2010, 23:30h to 6 Sept 2010, 5:00h (2 days)*
- 10 Sept 2010, 23:30h* to 12 Sept 2010, 8:00h (1 day)*
- 17 Sept 2010, 23:30h* to 19 Sept 2010, 8:00h (1day)*
*plus the night before and after
So far, three airlines – LOT Polish Airlines, Czech Airlines and Swiss Airlines – have announced their flight schedules for the period. The three carriers will operate services to Zurich, Prague, Budapest, as well as domestic flights to Cracow and Wrocław.
Travel Advice
Passengers scheduled to fly should contact their booking office for information on possible changes to flight schedules.